Project Location: Yandicoogina Mine Site, Newman, WA
Commence Date: July 2013
Completion Date: January 2014
Project Value: $ 2.5 Million
Overview: Yandi Sustaining project saw the expansion of Rio Tintos Accommodation requirements to an extra 496 accommodation rooms, this was part of an upgrade to existing site wide infrastructure,  JBP carried out the earthworks, concreting and building installation of the new double story accommodation camp.

Auguring Footings

Auguring Footings

1510487_215870981940263_149322631_n

JBP Equipment Arriving Onsite

JBP Employees Pouring Footings

JBP Employees Pouring Footings

Installing Accommodation Buildings